In Agile, how is visibility maintained in project status?

  1. By sharing detailed reports

  2. Through regular status meetings only

  3. Using artifacts like information radiators

  4. By limiting communication to management

The correct answer is: Using artifacts like information radiators

In Agile, visibility in project status is primarily maintained through the use of artifacts like information radiators. Information radiators are visual displays that provide real-time updates on the progress of the project. They include tools such as task boards, burndown charts, and other visual metrics that are easily accessible to all team members and stakeholders. This promotes transparency and allows everyone involved to stay informed about the current state of the project at any time. Utilizing information radiators ensures that important information is communicated effectively, empowering the team to make informed decisions and adjustments as needed. This approach aligns with the Agile principles of collaboration, flexibility, and responsiveness to change, which are essential for managing project dynamics. Other methods, such as sharing detailed reports or conducting regular status meetings, can contribute to visibility but may not be as effective in providing ongoing, real-time insights into project progress. Limiting communication to management would counteract the Agile philosophy, which emphasizes open communication and the involvement of all team members in the process.