What comprises the Product Backlog?

  1. All known features for a project, specific to each iteration

  2. All known features for a project, regardless of iteration or release

  3. The list of completed tasks for the current sprint

  4. A schedule of meetings and reviews for the team

The correct answer is: All known features for a project, regardless of iteration or release

The Product Backlog encompasses all known features, requirements, and enhancements for a project, regardless of how they are distributed across iterations or releases. This comprehensive list serves as the single authoritative source of what needs to be developed in the project, evolving over time as new requirements emerge and priorities shift. It not only includes new features but also considers technical debt, bug fixes, and other maintenance activities necessary for delivering a polished product. By maintaining a backlog that spans the entire project, teams can prioritize work based on business value, stakeholder feedback, and changing needs, enabling them to deliver incremental improvements throughout the project lifecycle. This practice aligns with the agile principle of embracing change and ensures that the team is always focused on the most valuable work at any given time. The other options do not accurately reflect the nature of the Product Backlog. Knowing features specific to each iteration would not capture the entirety of the required work and would limit the team's ability to adapt to new information. A list of completed tasks pertains to a specific sprint rather than future planning, while a schedule of meetings and reviews does not relate to the actual work or features needing development.