What occurs during an iteration retrospective?

  1. The team plans the next iteration

  2. The team evaluates the product backlog

  3. The team discusses completed work and processes for improvement

  4. The team performs a sprint review with stakeholders

The correct answer is: The team discusses completed work and processes for improvement

During an iteration retrospective, the primary focus is on continuous improvement. The team gathers to discuss the work that was completed during the iteration, reflecting on their processes, interactions, and practices. This discussion allows team members to identify what went well, what did not go as planned, and how they can improve their performance in future iterations. The retrospective fosters an environment of collaboration and openness where the team feels comfortable sharing observations and suggestions. This is crucial in agile methodologies, as it enables teams to adapt and optimize their workflow in a way that enhances efficiency and effectiveness. By concentrating on both completed work and areas for improvement, the retrospective helps in establishing actionable steps that can be integrated into the next iteration, thereby continuously enhancing the team's productivity and outcomes.